MINUTES OF THE MAY 14, 2007 REGULAR MEETING
OF THE PLAN COMMISSION OF THE VILLAGE OF
OAK BROOK APPROVED AS WRITTEN ON JUNE 18,
2007
CALL TO ORDER
CALL TO ORDER:
The Regular Meeting of the Plan Commission was called to order by Chairwoman
Payovich in the Samuel E. Dean Board Room of the Butler Government Center at
7:36 p.m.
ROLL CALL
ROLL CALL:
Gail Polanek called the roll with the following persons
PRESENT: Chairwoman Barbara Payovich, Members, Paul Adrian, Raju Iyer,
Gopal Lalmalani and Marcia Tropinski
IN ATTENDANCE: Barbara Gosselar, Assistant Village Attorney and Dale Durfey
Jr., Village Engineer.
MINUTES
APPROVAL OF MINUTES:
REGULAR PLAN COMMISSION MEETING OF MARCH 19, 2007
Motion by Member Adrian, seconded by Member Iyer to approve the minutes of the
March 19, 2007 Regular Plan Commission Meeting as written. VOICE VOTE:
Motion Carried.
UNFINISHED
UNFINISHED BUSINESS BUSINESS
There was no unfinished business to discuss.
NEW BUSINESS
NEW BUSINESS
A. WHITE AK MEADOW S — 3101 WHITE OAK LANE —FINAL PLAT _ MEADow
TWO -LOT SUBDIVISION FINAL PLAT -
TWO -LOT SUB
Chairwoman Payovich summarized the request. The owners of the property are
seeking final plat approval. There is a parcel of land approximately 2.5 acres that is
improved with a single family residence that will be demolished. The property
owners are seeking to subdivide the property into two parcels. One lot will be a flag
lot and both lots will have access to White Oak Lane.
Michael Guinta reviewed the request to subdivide the property into 2 individual lots.
Each lot will meet the R -2 standards and all Subdivision Regulation requirements.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 1 of 13 May 14, 2007
Each lot will have at least 1/2 acre of buildable area. At the time of building permit,
all grading plans will be submitted and will not impact the neighbors in any adverse
way. They are aware of the stormwater conditions in that area and their plan is to be
a good neighbor and work with them so that water is not shed on their properties. It
is their intent to build high quality structures that would be a compliment to the area.
They will be seeking to use the village water services.
Charles Shemely, President of the Heritage Oaks Private Roadway Association said
that they had conversations with their members that border this property. One has
had a problem that has been there for years. Their concern is not regarding the flag
lot or building nice homes, it has to do with how the property is managed in the
process, The property was improved with a tennis court and appears to be in a flood
plain. Water that used to flow over land in a natural watershed was put in a
stormwater pipe. There is an inlet in the center of the tennis court. They would like
to see if some situations that have gone from bad to worse in the past several years
could be corrected.
Karen Stacey, 3106 Heritage Oaks Lane, directly south of the property. She
reviewed the history of the property dating back to when they bought their property
in 1989. At that time, the entire pond was cleaned and the drain was kept opened.
She has concerns with the property. The pond does not drain adequately, because it
is always plugged and is not maintained. The drain tile is under the tennis court.
There is inadequate drainage that causes the pond to drain over its banks and covers
the entire peninsula, which can last for weeks; and one time it lasted for 6 months.
The flooding caused extensive erosion and she has lost 3 trees, with 3 more in
jeopardy. They would like for the following.
e The pond to drain naturally or a large pipe that is filtered to catch debris and
easily cleaned.
® The expense of the pond to be made known to the new owner and shared;
• The loss of land and property damage to be addressed and corrected;
The Village allowed the tennis court and adequate drainage was approved. The
Engineering Department has come out to the property when the property owner
could not be reached. She has had no recourse but to watch her land disappear.
Member Adrian appreciated her plight and suggested that Ms. Stacey work with the
applicant to work things out. The owner may not be aware of the situation so that it
can be rectified.
Mr. Guinta said that this was the first they have heard of this issue. Letters were
submitted to all of the neighbors prior to the Village's notices to the neighbors. He
included his phone number in the letter. He will work with her and come up with
the means to keep the drain from clogging.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 2 of 13 May 14, 2007
,1--�
Ms. Stacey said that she tried to resolve the issues on the property by calling the
realtor and the lawyer in order to bring it to their attention.
Mr. Shemdly said that Village Code Section, 14- 3 -3C.9 (Subdivision Regulations)
might apply to this issue as follows:
"No land which is subject to periodic flooding which lies in floodplain areas
as designated in title 9 of this code, or which contains inadequate drainage
facilities will be approved for occupancy in a subdivision, unless the
subdivider agrees to make all necessary improvements and agrees to all
required covenants which will, in the opinion of the village engineer, plan
commission and board of trustees make such land safe for occupancy, and
provide necessary safeguards for adjacent property which would be affected
by the filling, grading, drainage or other changes being permitted or required
for this subdivision."
He said that if you walk the property, it is obviously floodplain and it is a jungle of
swampy land. It would seem that the Plan Commission would have some
responsibility to look at this. Some permanent fixes should be put in and they are
looking out for the applicant as well as themselves.
Village Engineer Durfey noted hat it was number 5 in his memo (page 5) in the case
file. He did see the inlet on the site and it appeared that some water was flowing
into it from a southerly direction, but he did not see any pipes. He presumed that
there was an outlet pipe, but could not tell where things are or where they go until
some investigation is done.
Village Engineer Durfey noted that the item 4 in his memo is in regards to the
survey received that incorrectly depicted the limits of the pond. Item. 6 in the memo
also referred to the pond issues.
Assistant Village Attorney Gosselar said that from a legal perspective the issue is to
have enough information that it can be determined how Section 14- 3-3C.9 fits this
situation and what the Village can reasonably require to be done as a result.
Mr. Guinta said that when they received the review from the Village, they sent the
information to their surveyor to do the investigative work for items 4 -6 in Village
Engineer Durfey's memo; and they are having a very difficult time finding out
where the piping goes so they need to do some more homework. At this point, they
do not know and are attempting to address it and will continue to until they meet
staff s requirements and staff is satisfied that they are handling the water properly.
Mr. Guinta said that the surveyor has been to the site three times already and agreed
that the Village Engineer is waiting to hear from the surveyor.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 3 of 13 May 14, 2007
Member Adrian questioned if the issue needs to be looked at more from a legal
standpoint.
Assistant Village Attorney Gosselar responded that it did not. It is an engineering
matter as to how this requirement in the Subdivision Regulations is impacted by the
facts, as will be discovered, based on Dale's memo and the determination of the
topography and the status of the inlets.
Village Engineer Durfey said that at this time there are a lot of questions. It may be
a simple matter to fix or it may be a complicated and expensive matter; that is
unknown.
Member Adrian said that it appears more information is needed. Member Iyer
agreed.
Mr. Guinta said that they would do some more homework and resubmit it to the
Village if they decide to move forward.
It was agreed by the Plan Commission to continue the matter to the next meeting. If
the applicant is not able to move forward at that time a written request to continue
would be required.
Member Lalmalani moved, seconded by Member Iyer to continue the matter to the
next regular Plan Commission to allow the applicant time to resolve the engineering
issues and provide additional information to clarify the problem. ROLL CALL
VOTE:
Ayes: 5 -- Members Adrian, Iyer, Lalmalani, Tropinski and Chairwoman Payovich
Nays: 0 — None. Motion Carried.
5. B. DEERPATH WOODS —12 ACRES DEERPATH
LAN OF VACANT D LOCATED SOUTH WOODS -FINAL
OF 35t' STREET WEST OF ADAMS ROAD SOUTH AND EAST OF PLAT -F' E oT
BREAKENR.IDGE FARM UBDIVISION — FINAL PLAT — FIVE -LOT
SUBDIVISION
Gail Polanek, Planning and Zoning Administrative Technician summarized the
request. The Deerpath Woods preliminary plat was approved by the Village Board
on January 23, 2007. The applicant has now submitted the application for final plat
approval of the five -lot subdivision.
Steve Norga.ard, attorney for the applicant briefly reviewed the request. He noted
that there had been concerns with some residents regarding future access to
Breakenridge Farm Road and they worked through the problems, which have been
agreed to by the applicant and the Breakenridge Farm Subdivision owners. They are
now seeking final plat approval. There are some engineering issues to be resolved
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 4 of 13 May 14, 2007
and are seeking approval of the plat subject to engineering approval. This will allow
them to begin construction, during this construction season.
Jon Green, Project Engineer, Engineering Resources reviewed the final plat and said
that it was consistent with the approved preliminary plat. Each of the five parcels
proposed meet the minimum 2 -acre requirement for the R -1 zoned property. The
property is located on the west side of Adams Road south of 35th Street. Deerpath
Court is the proposed private road, which is consistent with the preliminary plat and
will be constructed to village standards, including pavement width, concrete curb,
gutter and storm sewer to handle the site drainage.
A subdivision entrance gateway has been added, including a gated entrance.
Landscape and subdivision entrance plans have been submitted. They have
augmented the shape and size of the entrance island. It is wider and longer to allow
some additional landscape planting and trees to the entrance. This was also a
condition of preliminary plat approval that the subdivision gateway be pushed back
off Adams Road to provide some separation, which they have done. Community
Development Director Kallien had commented on this issue in his Staff Report and
they have provided a 50 -foot setback from Adams Road, which allows adequate
room for vehicular stacking for those vehicles entering the subdivision.
There have been some conditions on water main approval made by staff. There are
portions of the existing water main being relocated. They have worked with Public
Works Director Meranda and Village Engineer Durfey to relocate the water main
within 15 feet of the new street. There was a concern on Lot 4 that some of the
existing water main was located too far from the street, so they are proposing to
relocate it at staff's request.
The plans have been submitted for the sanitary sewer, which is within the
jurisdiction of the Flagg Creek Reclamation District.
They have tweaked the design of the two detention ponds on the property. The
retaining walls as presented include the addition of some small retaining walls. They
are not walls intended to crain in more water storage, but rather walls to add some
intrigue and undulations to the detention pond. Many ponds are rectangular or
linear; these contours are a bit more intriguing. They worked with a landscape
consultant to put them together and some of the walls shown are actually built out of
large stone outcroppings, which are limestone type products and not the traditional
block wall. These present flattened plateaus and overlook areas for planting beds.
The walls as proposed are for aesthetical features and enhancements to draw the eye
to the ponds. They do not feel there will be any negative impact and the
homeowners association will maintain the ponds, which is consistent with the
maintenance of the private roadway and storm sewers. There will be adequate
access and safety with the ponds, which will include a safety ledge constructed
VILLAGE OF OAK BROOK May 14, 2007
Regular Plan Commission Minutes Page 5 of 13 y
below the normal water surface and constructed consistent with the village code and
standards.
He reviewed and responded to the comments made in the May 9, 2007 Staff Report
and Village Engineer Durfey's May 8, 2007 memorandum..
• Gate details relative to Adams Road -- provided on page 7 of the case file
• Drafting Revisions -- will revise per Village Engineer Durfey
• No vehicular access — will be added to the plat
• The Proposed roadway is consistent with preliminary plat approval.
• Tree Conservation Easement -- an arborist completed a detailed tree
inventory of the property and there are many large trees. It is the developer's
intent to create a tree preservation area on each of the properties. There are
larger tree preservation easements on the rear and sides of some of the
properties. It is intended that the homeowners association with covenants
and restrictions established will govern them.
• Tree Conservation Easement in the utility — was a stenographers error. The
intent is to keep the tree and utility easements completely separate.
• Gateway and Landscape plan — It was there understanding that the plan met
the intent of the code. They may need to add details in regards to species
and overlaying it on their CAD based engineering plan. They agree to
conform to that request.
• All other remaining items in the memorandum will be cornplied with and
submitted as part of the normal review process.
In summary, he said that the plan submitted is in substantial conformance with the
preliminary plat and meets the village code. On the basis of timing, being the peak
construction season and there is still the process of obtaining Village Board and
permit application approvals (i.e., village, water, sewer), they requested approval of
the plat conditioned upon the Village Engineer and staff approval.
Village Engineer Durfey reviewed his memorandum dated May 8, 2007 on page 8-
$.b of the case file.
• Private street comments was to advise everyone that the private streets,
included, private storm sewers and stormwater management facilities.
• Tree Conservation easement — there is just mislabeling of some items and he
is comfortable with that.
• Landscape easement — was explained by the applicant and the right language
will be used.
• Waivers and variations was handled at the preliminary plat stage
• Retaining walls was a concern at times with the village
• Stormwater Items. He has not yet received comments from the stormwater
consultant on the details and they are expected within approximately one
week.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 6 of 13 May 14, 2007
® Landscaping. A sketchy plan was received which lacks details and requires
revisions. A lot of information is still required as stated by Mr. Careen. The
Subdivision Regulations requires 40 -foot spacing with a minimum tree size.
The Public Works Construction Standards lists acceptable species and that
the locations are not near an underground utility.
Attorney Gosselar questioned whether these reviews were part of a staff function
rather than a Plan Commission review. Village Engineer Durfey responded that it is
a typical staff review like everything else. On occasion, the Plan Commission has
sometimes questioned tree species or other issues.
® Covenants, subdivision improvement agreement, subdivision security and
miscellaneous. (F, G, H, and I) typically come later on when the plans and
plat are fairly well developed and the final outcome can be seen, then the
various legal agreements and documents can be finished.
Chairwoman Payovich noted that there were not details provided on the retaining
walls.
Member Tropinski said that the property is not accessible to the general public and
she would be satisfied that at the time of permit they comply with the Village's code
requirements. The only concern would be with stormwater runoff and that would be
based upon the Village Engineers approval.
Member Iyer said that he also felt comfortable based upon the Village Engineers
approval. Member Adrian and Member Lalmalani agreed.
Member Adrian asked Village Engineer Durfey whether he was comfortable with
the applicant's responses to the outstanding issues.
Village Engineer Durfey said that he did not doubt that they would meet the Village
Code, there had not been enough time to review the changes to see if they had.
Attorney Norgaard said that they were ready, willing and able to comply with all
requirements.
Motion by Member Adrian, seconded by Member Iyer that the final plat is in
substantial conformance with the approved preliminary plat and the applicant has
satisfied the requirements of the Subdivision Regulations for approval of a Final Plat
of Subdivision of the five lot subdivision to be known as Deerpath Woods and is
subject to the following conditions:
1. All outstanding issues contained in Village Engineer Durfey's Memorandum
dated May 8, 2007 on pages 8 -8.b of the case file, including the drafting
VILLAGE OF OAK BROOK May 14, 2007
Regular Plan Commission Minutes Page 7 of 13 Y
revisions and approval of the stormwater, gateway, landscape and pond
design details.
2. Final Plat is subject to final Engineering approval.
ROLL CALL VOTE:
Ayes: 5 — Members Adrian, Iyer, Lalmalani, Trop
inski and Chairwoman
Payovich
Nays: 0 — None. Motion Carried.
S. C. BRITTWOOD CREEK -- 56 ACRES OF VACANT LAND LOCATED CRISEK SUB CrcEEK SUB —
SOUTH OF 35th STREET WEST OF BREAKENRIDGE FARM MALT AT
S1 DNISION AND EAST OF ROUTE 83 — FINAL PLAT — THIRTY -LOT SU13DIVISION
SUBDIVISION
Gail Polanek, Planning and Zoning Administrative Tecl- mician summarized the
request. The Village Board approved the Brittwood Creek preliminary plat of
subdivision on January 9, 2007. The approval reduced the number of lots to 30.
The applicant has now submitted the application for final plat approval of the thirty -
lot subdivision.
Walter Morrissey, attorney for the applicant provided an overview of the request. A
letter of review from the Forest Preserve District of DuPage County was received
and made part of the case file.
The property is 56.3 acres. The previous property owner conveyed a portion of the
original parcel to the Oak Brook Farms. The approved ordinance provides for 11
lots to be zoned R -1, 2 -acre plus parcels and are located along the eastern perimeter
of the property. There are 10 lots zoned R -2, 1 -acre plus lots along Route 83 and
there are 9 lots in the interior that are zoned R -2, and are 1.4 to 1.5 acre in lot area.
A secondary access has been added at 35 Street. The applicant is cooperating with
the Village to seeking approval from IDOT to allow for an emergency access off of
Route 83 onto 35th Street, which would be restricted to use only by police, fire and
paramedic vehicles. There is a berm along the western boundary of the property.
They will be seeking a variation in order to install an 8 -foot solid fence on top of the
berm. The Village Engineer noted some changes in lots 5 and 6 that will be
transferred to 2 properties in Breakenridge Farm. The lots remain conforming and
are permissible transfers under the Plat Act.
Dan Callaghan, developer and property owner, provided a review of the plat. He
said that staff has noted in their reviews that the substance of what has been
submitted adheres to all of the ordinances. There are some things that are still
required, but he is very familiar with stormwater management and wetland
requirements and has worked with Village Engineer Durfey in the past. They will
complete the required declarations to cover the private streets, as well as storm
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page $ of 13 May 14, 2007
services and detention. The Subdivision Improvement Agreement will also be
completed with staff review and approvals. The 30 -lot subdivision final plat as
presented at this meeting is what was approved at the preliminary plat stage. Large
conservation easement areas have been created. They have complied with the intent
of the ordinance on the landscape plans. He does not cut corners with landscaping
with what he tries to accomplish. The front entrance remains unchanged with the
gates and the wall. The design on the gatehouse windows was changed somewhat.
The biggest change made was to the western berm and the landscaping. He is
seeking approval of a variation in order to construct a solid wood fence. He
provided a sample of the material to be used on the fence. The color is earth tone
and the material will not have a commercial effect, The original plan depicted a
decorative retaining wall within the subdivision and the loop road. During the
detailed review of the final plans, it appeared to be commercial looking. He
requested that the engineers leave as much of the site alone as possible to prevent
the loss of trees and so he had the engineers mass earth balanced the entire site. If
he stayed with the original plan, he would have had to truck fill in for the berm,
which could have totaled 1,000 semi -truck loads. Along areas of Route 83 there are
3 -4 foot high concrete walls with an 8 foot fence on top, which looks very nice even
without landscaping in front of it. He has proposed instead of a very tall concrete
wall, to use a similar sized concrete wall with a Trex fence on top. The Trex fence
material is a 50 -year product. They would also agree to remove the fence, in the
event that Route 83 would ever be widened. This fence will be set 3 feet inside of
the subdivision property line. The revised design looks much more natural looking
than the original and would better compliment the subdivision and will soften the
look. Pictures of the view from Route 83 were also submitted to show the existing
dense 50 feet of vegetation that will be in front of the fence. The existing vegetation
will hide 60 -80% of the fence. The fence will serve as a sound barrier as well as a
visual barrier to Route 83.
Jon Green, Engineering Resource reviewed the stormwater aspects of the project.
Final engineering plans and a final engineering stormwater management report have
been submitted for review. It is consistent with the Village and DuPage County
requirements. Some aesthetic adjustments were made to some of the ponds on the
property. There are several ponds placed strategically throughout the subdivision
that are consistent with the natural flow patterns of the property. It has been their
goal to preserve as many of the natural features of the property, without doing any
mass earthwork and saving many of the trees as possible. The ponds behind lots 11,
12 and 30 are known as the wetland mitigation ponds. Those ponds will have very
small bounce in water levels and will be planted strategically with emergent
plantings consistent with the Army Core and County requirements. The developer
has shown compliance with mitigation requirements on other projects in town.
A couple of ponds on the property do have retaining walls on them; there was a staff
concern during the preliminary process that some of the walls were a bit tall. Some
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 9 of 13 May 14, 2007
revisions were made to the wall scheme and height (3 1/2 feet at their tallest point).
The location of the retaining walls is just on the outside of the creek side by the
ponds behind lots 4, 5, 7 and 8. There is quite a bit of terrain and natural fall off,
some around 15 -20 feet from front to rear. They are doing what they can to preserve
the pad sites natural features. They are preserving the existing wetlands and there
will be no impact on the floodplain areas. They have proposed a conservation
wetland buffer between 25 -50 feet from the wetlands. The retaining walls are
needed to absorb grade and to preserve the buffer and natural features as a buffer to
the existing property east of the subdivision.
The stor-mwater release rate conforms to the Village Code. The proposed project
will substantially reduce the runoff of the 100 -year peak event from its current
condition. All ponds will be aesthetically pleasing.
Matt Thumm, Ives, Ryan & Associates, summarized the landscape plans, There are
roughly 900 trees for 30 lots, which is about 30 trees per lot, which there are not
many that meet that kind of a standard. In addition to the landscape buffer, there are
evergreen screens along Route 83 along with under plantings. There will be
deciduous trees along the ring road along with ornamental grasses and perennials.
They are trying to convey a rustic country estate image as you enter and throughout
the development. Complying with DuPage County requirements along the creek
area there are a number of mitigation trees being added as well. They will be doing
repairing and enhancement along the area to improve the woodlands, in addition to
saving a lot of the trees for the residents benefit. There will be natural plantings and
prairie areas.
Mr. Morrissey said that there were several changes to the preliminary plat when it
was before the Plan Commission. He noted that the plat of subdivision has some
notes in the upper hand corner that memorializes the agreement that was reached
with the neighbors. An easement agreement was entered into with Mr. Vendel, Oak
Brook Farms. Outlot V was not part of the preliminary plan; it will be open space in
perpetuity, and as long as Mr. Vendel or his heirs are operating the farm there is the
opportunity for the users of the services of the facility to graze horses and use it for
transit.
A covenant was recorded against the entire 56 acres that guarantees that the
subdivision will have no more than 30 lots and provides that the lots cannot be
resubdivided into smaller lots at a fixture date, by a future owner or future board. The
covenant also provides that there is a no access provision to Breakenridge Farm
Road.
Chairwoman Payovich asked for a consensus among the Commissioners on how to
proceed with the plat review.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 10 of 13 May 14, 2007
Member Tropinski said that she would like more time to review it for the
stonnwater detention and runoff She also would like more information on the
ponds that occur in wetlands and floodplain. There is an ingress easement and the
pond and can it be safely accessed.
Mr. Green responded that final engineering plans have been submitted as a
supplement to the final plat. Those plans along with detailed landscape plans
specify where the wetland plantings are. The plans also describe the floodplain
limits on the topographic maps. They area limited to the Bronswood area of the
property.
Member Lalmalani questioned Village Engineer Durfey regarding the ponds not
meeting the Public Works Standards.
Village Engineer Durfey responded that the engineering plans had some typical
cross sections for the lakes and ponds. When he initially perused them, he noticed
that they did not match the typical detention and cross section in the Public Works
Standards or a vegetated ecological planted area. They are not ready to conclude
anything at this point.
Mr. Green said that the proposed detention pond section is kind of a hybrid of a
natural style wetland type basin and a village standard basin. In keeping with the
rural character of the project and keeping the pond section somewhat consistent with
Village, they believe that it can be worked out to the satisfaction of the Village staff
as part of the engineering review.
Mr. Callaghan said that the ponds at Forest Gate as well as some other ponds in the
Village do not always fit in the square box. The stormwater management, wetlands,
and ponds have all been engineered per the Village and DuPage County Stormwater
Management Ordinance. They are quite similar to Forest Gate. There will be sod
going to the waters edge and there will be (approximately one and one -half foot
below the water surface), an 8 -foot wide safety shelf, so that if anyone would fall
into the pond, there is a safety so that someone could stand up on it to come out.
The concern for safety is even better than Forest Gate because there is a 3 to 1 slope
coming out of the water; these ponds are 4 to 1, which is a significant difference.
There is a more gradual slope on these ponds. They have discussed and agreed
regarding the slopes coming out of the pond. They have not had a lot of time to
review it with Dale. He feels confident that they will work this out as well.
Member Adrian questioned the proposed wall by Route 83.
Mr. Callaghan said that the eight -foot fence goes on top of the four -foot wall, so
there would be a total of about 12 feet.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 11 of 13 May 14, 2007
Assistant Village Attorney Gosselar questioned the waiver for the street light system
and noted that it would have to include it in the recommendation.
Mr. Callaghan said that the street light standard for the village is appropriate for
Jorie Blvd., but not for a subdivision. The style chosen for the proposed streetlights
is almost the style as the street signs that are in the village, which includes the
decorative cast iron post and compliments the environment of the subdivision, rather
than the village standard square box and pole.
Chairwoman Payovich said that the concern is the length and number of issues
raised in Village Engineer Durfey's memorandum and would like a report from him
that the majority of these things had been taken care of
Member Iyer said that although many are minor in nature there are a number of
issues that are unclear.
Chairwoman Payovich was concerned with the unresolved stormwater issues and
although the developer is not at fault; but rather it is a complex matter and staff has
not had sufficient time to review it.
Member Adrian said that he believes everything presented are things that can be
addressed by the Village Engineer, but would like to receive a report from Dale that
many of the issues are addressed because he felt that the Plan Commission has that
responsibility; the project looks like it will be wonderful. Member Lamalani agreed.
Mr. Callaghan noted that the pond details were on sheets, 5, 6, and 7 of the
engineering plans, shows the streets, the location of the ponds the 2 to 1 slopes and
the safety shelf in the pond. Ms. Polanek said that the sheets with the details could
be emailed to the Plan Commission for review and the members agreed.
Mr. Callaghan noted that there is a horse riding trail easement added
on the, property. For the past 18 years, Mr. Gothard allowed Mr. Vendel to use property
to ride the horses. In the homeowner declaration, they will provide the right for the
homeowners association to allow them to enter into a yearly license agreement with
Mr. Vendel as to its use. He would be required to do daily maintenance e rov drug
manure, which is required under the county ordinance, p
insurance to the homeowner association. The actual cost of construction and the
annual cost to continue the structural integrity of the trail will reside with the
homeowners association. For the first three years, the lease will cost Mr. Vendel,
one dollar.
Village Engineer Durfey questioned whether the proposed structure on top of the
berm is a fence or a noise wall. There are no provisions in the ordinance for noise
walls, just fences.
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 12 of 13 May 14, 2007
0
7
Mr. Morrissey responded that they are looking at it as a solid fence rather than a
chain link fence, because it is the most appropriate way to be contiguous and follow
the intent of the ordinance. The fence will have the ability to mitigate sound, but
they are not making a representation to that.
Motion by Member Adrian, seconded by Member Iyer to continue the hearing on the
Brittwood final plat to the next regular meeting and the applicant is to address the
issues in Village Engineer Durfey's memorandum ROLL CALL VOTE:
Ayes: S --- Members Adrian, Iyer, Lalmalani, Tropinski and Chairwoman Payovich
Nays: 0 — None. Motion Carried.
OTHER BUSINESS
There was no other business to discuss.
ADJOU]L2NMENT:
Motion by Member Lalmalani, seconded by Member Adrian to adjourn the meeting
at 9:41 p.m. VOICE VOTE: Motion carried.
ATTEST:
Robert Ka11i Direct ommunity Development
Secretary
VILLAGE OF OAK BROOK
Regular Plan Commission Minutes Page 13 of 13 May 14, 2007
OTHER
BUSINESS
ADJOURNMENT