G-821 - 01/09/2007 - COMMUNITY DEVELOPMENT - Ordinances Supporting DocumentsG
qG'F -�-
CO -T1,
co
O
ITEM iL-H.
AGENDA ITEM
Regular Board of Trustees Meeting
of
January 9, 2007
SUBJECT: Increase in Building Code Fees
FROM: Kenneth T. Kubiesa, Village Attorney
BUDGET SOURCE /BUDGET IMPACT: N/A
RECOMMENDED MOTION: I move for passage of Ordinance G -821, An Ordinance
Amending Section 10 -4 -1 ( "Fee and Bond Schedule ") of Chapter 4 ( "Fees and Bonds ") of
Title 10 ( "Building Regulations ") of the Village Code of the Village of Oak Brook to
Establish a Revised Fee and Bond Schedule for Permits, Applications, Plan Review and
Inspections.
Background /History:
Pursuant to your direction and the recommendation of the Community Development Department,
we have prepared the attached Ordinance which amends Chapter 10 of the Village Code to
increase the Building Code fees.
Recommendation:
I recommend that Ordinance G -821 be passed.
Last saved by Default J \ALL DOMBOARD MEMOS\Bldg Fees05 doc
Last printed 1/3/2007 3 23 PM 0�
y
��l r
•
� E
i t a a�E E En H6,
i3 s
�: >a� �r :.��_: .�w�E<:..a°a:;.: °�i:� x >� - n�s��rj y�sl ;•,s�..�.�.. "a 8.. �si� . >�g� ..�� � ��.,
"r •
I
AGENDA ITEM
Regular Board of Trustees Meeting
of
December 12, 2006
SUBJECT: Amendment to Title 10 of the Village Code —Chapter 4 Building Regulations —Fees
FROM: Robert L. Kallien, Jr., AICP, Community Development Director
BUDGET SOURCE /BUDGET IMPACT: N/A
RECOMMENDED MOTION: I move that the Village Board approve the recommended
changes to the Fee Schedule in Chapter 10 — Building Regulations and authorize the Village
Attorney to prepare the necessary ordinance for final consideration at the January 9, 2007
meeting.
Background /History:
Beginning in 2001, the Village Board has approved annual updates to the fee schedule in Chapter
10 — Building Regulations relative to fees associated with new construction activities (e.g. permits,
plan review and inspections). At that time, the Board directed that the fee schedule be updated each
year to ensure that a goal of cost recovery be met.
Proposed Update
Consistent with the Board's goal to cover Staff costs; the fee schedule applicable to our building
regulations has been updated. Since our estimated 2007 costs are proposed to increase by
approximately 5 percent, each of the individual fee amounts have been updated by that amount.
Some exceptions can be found where rounding was necessary or where the previous fee was found
to be insufficient to our cover costs.
One additional change that is being recommended in this update is the need to refine the fee
assessed for residential tents. Since these tents are used by residents for special events that usually
last no more than a day, a base fee of $30 per tent is being recommended which is less than the $92
fee for commercial tents.
Last saved by administrator I \ComDev \GPOLANEK \l -FROM BOB\Bot - PC - ZBA\BO- Rec- Building Fees -2006 doc
Last printed 12/6/2006 12 25 PM
Recommendation:
The revised fee schedule (see attached) recommended for your consideration will generate
additional revenues and provide a mechanism to continue the Board's goal to cover the costs of all
Village staff involved in the review and approval processes related to new construction.
Last saved by administrator I \ComDev \GPOLANEK \1 -FROM BOB\Bot - PC - ZBA \BO- Rec- Building Fees -2006 doc
Last printed 12/6/2006 12 25 PM
CHAPTER 4
FEES AND BONDS
SECTION
10 -4 -1 Fee and Bond Schedule
10 -4 -1: FEE AND BOND SCHEDULE: Before a permit required by this Title is issued, the
M
Director of Community Development shall collect a fee and bond calculated
according to the following schedule
Volume Computation. Volume shall be computed on the exterior dimensions of the building
and shall include all space above the lowest level of the foundation wall and to the highest
point of the main roof and to include all projections
B. Unit of Volume Cost. Figure a fraction larger than one -half (1/2) as a full unit
Proposed
Current
Fee ($)
Fee ($)
1
New Buildings:
Commercial, Office and Industrial
Base permit fee
$113400
$108000
Plus $9 00 per 1,000 cubic feet
$ 8 75
Residential
Base Permit Fee
$ 625.00
$ 595 00
Plus $3.25 per ea additional 1,000 cubic feet.
$ 300
2
Residential Additions and Alterations .
Base permit fee
$ 12400
$ 11800
Plus $12.25 per 1,000 cu.ft
$ 11 90
3.
Commercial Additions and Alterations
Base permit fee
$ 310 00
$ 295 00
Plus $6 25 per $1000 est cost of new construction
$ 600
4
Plumbing Work
Per plumbing fixture or opening
$ 1250
$ 1195
Septic system installation
$ 14200
$ 13500
Septic system repair
$ 14200
$ 13500
5
Electrical Work.
Electrical Permit (base fee)
$ 63 00
$ 6000
Residential service
To 100 amps
$ 5000
$ 4800
To 200 amps
$ 61.00
$ 5800
To 300 amps
$ 7400
$ 7100
R1
a
To 400 amps
$ 8600
$ 8200
Over 400 amps
$ 100.00
$ 9500
Commercial service-
To 100 amps
$ 3700
$ 3500
To 200 amps
$ 5000
$ 4800
To 300 amps
$ 6100
$ 5800
To 400 amps
$ 7400
$ 71 00
To 600 amps
$ 86.00
$ 8200
To 800 amps
$ 10000
$ 9500
To 1,000 amps
$ 11300
$10800
To 2,000 amps
$ 18800
$17900
To 3,000 amps
$ 250.00
$23800
Over 3,000 amps
$ 375 00
$35700
Commercial Circuits (each)
$ 1250
$ 11 95
Commercial openings, (each)
$ 325
$ 2.95
Commercial devices — alarms, strobes, detectors (each)
$ 3 25
$ 295
Commercial Motors (each)
Up to 20 hp
$3200
$3000
Each additional hp over 20 hp
$ 325
$295
Commercial Appliances (each)
Up to 20 kw
$ 3200
$30.00
Each additional kw over 20
$ 650
$ 625
Commercial — Temporary installations
$ 92.00
$ 88 00
Commercial Communication /Alarm (signal /low voltage) Systems
$ 5700
$ 54 00
Driveway -
Commercial
$ 310 00
$ 295 00
Residential
$ 7400
$ 71 00
Certificates of Occupancy and Compliance (each)-
$ 32.00
$ 3000
Accessory Buildings and Structures (each)
Pools, hot -tubs, detached garages, commercial tents,
$ 9200
$ 8800
Decks, patios, fireplaces, flagpoles and
Other similar structure
Residential Tents
$ 3000
$ 8800
Elevators, Escalators, Dumbwaiters
Elevator /escalator
5 floors or less, per device
$ 9200
$ 8800
Each additional floor over 5
$ 2000
$ 1900
Hand - operated, 5 floors or less
$ 44.00
$ 4200
Hand - operated, each floor over 5
$ 20.00
$ 19.00
Inspection certificate, biannually, each
$ 9200
$ 8800
Dumbwaiter
5 floors or less
$ 8800
Each additional floor over 5
$ 2000
$ 1900
Hand - operated, 5 floors or less
$ 44.00
$ 42.00
Hand - operated, each floor over 5
$ 20.00
$ 19.00
Inspection certificate, biannually, each
$ 9200
$ 8800
10
Mechanical Heating, Cooling, Ventilating Systems
including Chimneys
Each mechanical device /appliance
$ 61 00
$ 5800
11
Storm Sewer /Sump Pump Connection (each)
$ 9200
$ 8800
12.
Canopies, Marquees
$ 6100
$ 5800
13.
Tanks, Flammable and Nonflammable.
500 gallons or less
$ 9200
$ 8800
Over 500 gallons, $5.25 ea. additional 100 gallons
14.
Recoat or Recover Roof:
Residential
$ 6100
$ 5800
Commercial
$ 625 00
$ 595 00
15
Temporary Office or Construction Trailer (each)
$ 12400
$ 11800
16
Fences (each):
$ 6100
$ 58.00
17.
Signs
Per square foot
$ 3 50
$ 3 15
Minimum
$ 59 00
$ 56 00
18
Moving Buildings•
$ 310 00
$ 295 00
19
Wrecking Demolition, Shoring, Raisings, Underpinning
Base fee
$ 275 00
$ 260 00
Plus 3 00 Per 1,000 cu ft.
$250
20.
Plan and Application Examination and Review-
Each, per hour
$ 5100
$ 4900
Minimum fee
$ 5100
$ 4900
In the event that any outside consulting plan review services are used, the applicant
shall
reimburse the Village for any fees associated with that service as a prerequisite to the issuance
of any required permits
21
Inspection Fee (each)
$ 5100
$ 4900
A fee based on the estimated number of inspections will be assessed
prior to permit
issuance
Additional inspections will require payment of an additional fee.
22
Cleanup and Street Bond
Commercial
$ 650 00
$ 595.00
Residential
$ 325 00
$ 295 00
23
Completion Bond
Each $ 625 00 $ 595 00
24. Starting Work Without a Permit:
Each $ 15000 $ 140.00
25. Occupancy of a Building or Structure Without Final Inspection and/or Issuance of Occupancy
Permit
Each $ 15000 $ 14000
26 Application Fee (required for each permit application) $ 3200 $ 3000
C Certain Entities Permitted to Request Waiver Any governmental unit or any charitable
organization, as defined in an Act to Regulate Solicitation and Collection of Funds for
Charitable Purposes, may request a waiver of any fees imposed pursuant to the terms of this
Section Upon such requests, the Village President and the Board of Trustees may, by motion,
waive any such fees imposed pursuant to this Section