R-1756 - 10/09/2018 - FIRE DEPARTMENT - Resolutions RESOLUTION 2018-FD-SR-CNTRCT-R-1756
A RESOLUTION APPROVING AND AUTHORIZING THE AWARD AND
EXECUTION OF A CONTRACT FOR THE FIRE STATION 93 SHOWER ROOMS
PIPING AND VALVE REPLACEMENT PROJECT BY AND BETWEEN THE
VILLAGE OF OAK BROOK AND COMPLETE CONSTRUCTION RESOURCES
WHEREAS, the Village of Oak Brook ("Village") desires to improve the shower
rooms at Fire Station 93, by replacing the piping, valves, shower pans, and repairing the
walls and floors ("World'); and
WHEREAS, the Village solicited bids for the completion of the Work, pursuant to
which the Village received five bids; and
WHEREAS, Complete Construction Resources of Chicago Heights, Illinois
("Complete Construction Resources"), is the lowest responsive and responsible bidder
for the completion of the Work; and
WHEREAS, the Village and Complete Construction Resources desire to enter into
and execute a Contract for the completion of the Work in an amount not to exceed
$55,400.00 ("Contract'), which Contract is attached to this Resolution as Exhibit A; and
WHEREAS, the President and Board of Trustees have determined that it is in the
best interest of the Village to enter into the Contract with Complete Construction
Resources;
NOW THEREFORE, BE IT RESOLVED BY THE PRESIDENT AND BOARD OF
TRUSTEES OF THE VILLAGE OF OAK BROOK, DU PAGE AND COOK COUNTIES,
ILLINOIS as follows:
Section 1: Recitals. The foregoing recitals are hereby incorporated into, and
made a part of, this Resolution as the findings of the President and Board of Trustees of
the Village of Oak Brook.
Section 2: Approval of the Contract. The President and Board of Trustees
hereby approve the Contract by and between the Village and Complete Construction
Resources in substantially the same form attached to this Resolution as Exhibit A, and in
a final form acceptable to the Village Attorney.
Section 3: Authorization and Execution of the Contract. The Village Manager
and Village Clerk shall be, and hereby are, authorized to execute the Contract on behalf
of the Village after receipt of the final Contract fully executed by Complete Construction
Resources.
Resolution 2018-R-1756
Award of Contract for Fire Station 93 Shower Rooms Piping and Valve Replacement Project
Page 2 of 3
Section 4: Effective Date. This Resolution shall be in full force and effect upon
passage and approval in the manner provided by law.
[SIGNATURE PAGE FOLLOWS]
Resolution 2018-R-1756
Award of Contract for Fire Station 93 Shower Rooms Piping and Valve Replacement Project
Page 3 of 3
APPROVED THIS 9th day of October , 20
Gopal G. Lalmalani
Village President
PASSED THIS 9th day of October 12018
Ayes: Trustees Cuevas, Saiyed, Yusuf
Nays: Trustees Manzo, Tiesenga
Absent: Trustee Baar
ATTEST:
OF 041,
+ " - Charlotte K. Pruss
; Village Clerk
�ffP�TY��
Resolution 2018-R-1756
Award of Contract for Fire Station 93 Shower Rooms Piping and Valve Replacement Project
Page 4 of 3
EXHIBIT A
CONTRACT
4824-0556-3246,v. 1