Pre-Bid Meeting Minutes 082516Meeting Minutes
Project [14-172-872 Ph 1] - Village
of Oak Brook - Heritage
Center Renovations
View Date 8/26/2016
Kluber, Inc.
10 S. Shumway Ave.
Batavia, IL 60510
Phone: (630) 406-1213
Meeting No. 14-172-872
Ph 1-003
Meeting
Type
Pre-Bid
Subject Heritage Center - Phase 1 Exterior
Renovations & Improvements
Prepared
By
Jeff Bruns, S.E., LEED AP
Date 8/25/2016
Time 11:00 AM CT
Location Butler Goverment Center, Oak Brook, IL
Meeting Attendance
Company - Attendee Required Attended Company - Attendee Required Attended
Kluber, Inc. - Jeff Bruns,
S.E., LEED AP
Village of Oak
Brook - Rania Serences
Village of Oak
Brook - Darren Martens
Ordered By Item No.
14-172-872-003-001
Summary Project Team
Desired
Outcome
Understanding of complete project team, the primary
contacts, and authorized representatives.
Originated
Due
Resolved
Complete
Discussion Details
1. Kluber Architects + Engineers
a. Jeff Bruns, SE, Project Manager
2. Village of Oak Brook
a. Darren Martens, Village of Oak Brook
b. Rania Serences, Senior Purchasing Agent
3. Project Work Site
a. The Heritage Center, 1112 Oak Brook Road, Oak Brook, IL 60523
No comments, all understand.
14-172-872-003-002
Summary Invitation for Bidder's Proposals
Desired Outcome Understanding of Bid Form and Supplements.
Originated
Due
Resolved
Complete
Discussion Details
1. Scope of Work:
a. Removal and replacement of site retaining walls, removal of abandoned fuel tank,
removal and replacement of exterior slab, waterproofing and associated elements.
Page 1 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
b. Alternate bid No. 1: Basement area below the slab will be filled in, foundations removed,
water proof door opening, in-filled and lab on grade installed for condusor.
2. Bid package consists of the following documents:
a. Invitation for Bidder’s Proposals;
b. General Instructions to Bidders;
c. Addenda, if any are issued during the bidding process;
d. Bidder’s Proposal;
e. Bidder’s Sworn Acknowledgement;
f. Bidder’s Sworn Work History Statement;
g. Other information submitted by Bidder, if requested during the bidding process;
h. Notice of Award; and
i. Contract, including all of its attachments and appendices, if any.
3. Inspection and examination of bid documents.
a. Via the Internet at www.oak-brook.org, at no charge.
b. A paper hard copy may be obtained in person from Owner’s Purchasing Division, Butler
Government Center, 1200 Oak Brook Road, Oak Brook, Illinois 60523 for a $25.00 non-
refundable copy fee.
4. Pre-Bid Meeting: Every prospective bidder is required to attend a Bid Meeting scheduled for
11:00 A.M., Thursday, August 25, 2016, in the Samuel E. Dean Board Room, at the
Butler Government Center located at 1200 Oak Brook Road, Oak Brook, Illinois 60523,
to review the scope of the improvements and the project specifications. Failure to attend this
mandatory meeting will disqualify the bidder.
a. Make sure you have signed in on the Sign-In sheet.
b. Leave business card with all contact information.
5. Bid Opening: Owner will receive sealed Bidder’s Proposals for the Work until 11:00 a.m., local
time, Thursday, September 1, 2016, in the Samuel E. Dean Board Room, at the Butler
Government Center located at 1200 Oak Brook Road, Oak Brook, Illinois 60523, at which time,
or as soon thereafter as possible, all Bidder’s Proposals will be publicly opened and read aloud.
Bidders or their agents are invited to be present.
6. Bid Security, Bonds and Insurance:
a. Bid Security. Each Bidder’s Proposal shall be accompanied by a security deposit of at
least 5 percent of the Bidder’s Price Proposal in the form of (1) a Cashier’s Check or
Certified Check drawn on a solvent bank insured by the Federal Deposit Insurance
Corporation and payable without condition to Owner or (2) a Bid Bond in a form
satisfactory to Owner from a surety company licensed to do business in the State of
Illinois with a general rating of A minus and a financial size category of Class X or better
in Best’s Insurance Guide.
b. Performance and Payment Bonds. The successful Bidder will be required to furnish a
Performance Bond and a Labor and Material Payment Bond on award of the Contract,
each in the penal sum of the full amount of the Contract Price, on forms provided by, or
otherwise acceptable to, Owner, from a surety company meeting the requirements set
forth above. Each Bidder’s Proposal must be accompanied by a letter from such a surety
company stating that it will execute Bonds on forms provided by, or otherwise acceptable
to, Owner, on award of the Contract to Bidder.
c. Insurance. The successful Bidder will be required to furnish certificates of insurance as
required by Section 4.2 of the Contract on award of the Contract. Each Bidder’s Proposal
must be accompanied by a letter from Bidder’s insurance carrier or its agent certifying
that said insurer has read the requirements set forth in the Contract and will issue the
required certificates and policies of insurance on award of the Contract to Bidder.
No comments, all understand.
14-172-872-003-003
Summary General Instructions to Bidders
Desired Outcome Understanding of Bid Form and Supplements.
Originated
Due
Resolved
Complete
Discussion Details
Page 2 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
1. Addenda, if required, will be issued prior to bid opening and shall become part of the Bid
Package. Intent is to issue final addenda no later than August 29, 2016.
2. Prevailing wages are required.
3. Owner is exempt from state and local sales, use, and excise taxes.
4. Contractor shall be responsible for applying for and obtaining all permits. Permit fees
associated with the Village of Oak Brook Building Department will be waived.
5. Bid security is required.
6. Time of award, if contract is awarded, will be made within 45 days following the opening of
bidder's proposal.
7. Any questions, clarifications or substitution requests need to occur in writing via email to
jbruns@kluberinc.com Oral or other interpretations or clarifications will be without legal effect.
a. Note: Last day to submit questions, substitution requests for incorporation into addenda
will be August 26, 2016, at 2:00 p.m.
b. Responses will be emailed to all bidder's present at the pre-bid meeting.
No comments, all understand.
14-172-872-003-004
Summary Bidder's Proposal
Desired Outcome Understanding of general bidding criteria.
Originated
Due
Resolved
Complete
Discussion Details
1. The bidder's bid proposal includes the following:
a. Proposal
b. Sworn Acknowledgement
c. Sworn Work History
d. Notice of Award
No comments, all understand.
14-172-872-003-005
Summary Contract Terms
Desired Outcome Understanding of contract terms.
Originated
Due
Resolved
Complete
Discussion Details
1. The bidder's contract with the Village of Oak Brook includes the following:
a. Article I = The work
b. Article II = Changes and Delays
c. Article III = Contractor's Responsibility for Defective Work
d. Article IV = Financial Assurances
e. Article V = Payment
f. Article VI = Disputes and Remedies
g. Article VII = Legal Relationships and Requirements
h. Attachment A = Supplemental Schedule of Contract Terms
i. Attachment B = Specifications
j. Attachment C = List of Drawings
k. Attachment D = Special Project Requirements
1. Appendix 1 = Prevailing Wages
2. Appendix 2 = Form of Performance Bond
Page 3 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
3. Appendix 3 = Form of Labor and Materials Bond
No comments, all understand.
14-172-872-003-006
Summary Preliminary Schedule
Desired Outcome Understanding of project schedule.
Originated
Due
Resolved
Complete
Discussion Details
1. Award of Contract: September 13, 2016
2. Contractor to apply for Building permit: No later than September 15, 2016
3. Commencement of Construction: October 3, 2016
4. Substantial Completion: November 30, 2016
No comments, all understand.
14-172-872-003-007
Summary Summary (Section 01 10 00)
Desired Outcome Understanding of project summary.
Originated
Due
Resolved
Complete
Discussion Details
1. Contract Description
a. Contract Type: A single prime contract based on Lump Sum contract as described
in the Village of Oak Brook Contract for the Construction of Phase 1 Heritage
Center Exterior.
2. Description of Alterations Work
a. Scope of demolition and removal work as shown on drawings and specifications.
b. Scope of underground storage tank removal work is shown on drawings and
specifications.
c. Scope of alterations work is shown on drawings and specifications.
3. Work by Owner
a. Owner will contract and/or self perform for the minor electrical, lighting, fire
protection and removal of the existing condensing unit on the slab in order to
remove and replace the exterior slab. This includes demolition and re-installation
of such items.
b. Owner will supply and install landscape restoration over excavated and filled areas
4. Owner Occupancy
a. Owner intends to continue to occupy adjacent portions of the existing building
during the entire construction period.
b. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
c. Schedule the Work to accommodate Owner occupancy.
5. Contractor use of Site and Premises
a. Construction Operations: Limited to areas designated by Owner.
b. Provide access to and from site as required by law and by Owner.
1. Emergency Building Exits During Construction: Keep all exits required by
code open during construction period; provide temporary exit signs if exit
routes are temporary altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
c. Existing building spaces may not be used for storage
d. Utility Outages and Shutdown:
1. Limit disruption of utility services to hours the building is unoccupied.
Page 4 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
2. Do not disrupt or shut down life safety systems without 7 days notice to
Owner and authorities having jurisdiction.
3. Prevent accidental disruption of utility services and other facilities.
No comments, all understand.
14-172-872-003-008
Summary Temporary Facilities and Controls (Section 01 50 00)
Desired Outcome Understanding of Project scope.
Originated
Due
Resolved
Complete
Discussion Details
1. Temporary Utilities
a. Owner will provide the following:
1. Electrical power metering, consisting of connection to existing facilities.
2. Water supply, consisting of connection to existing facilities.
2. Telecommunications Services shall include:
a. Cellular Phone: Site Superintendent, Project Manager and all sub-contractors are
required to carry mobile cell phones.
3. Temporary Sanitary Facilities: Use of existing facilities located at Heritage Center permitted.
4. Barriers: Provide barriers to prevent unauthorized entry to construction areas, to prevent
access to areas that could be hazardous to workers or the public, to allow for Owner's use of
site and to protect existing facilities and adjacent properties from damage from construction
operations and demolition.
5. Fencing:
a. Construction: Commercial grade chain link fence.
b. Provide 6 foot high fence around construction site.
6. Exterior Enclosures: Provide temporary weather tight closure of exterior openings to
accommodate acceptable working conditions and protection for Products, to allow for temporary
heating and maintenance of required ambient temperatures identified in individual specification
sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing
hardware and locks.
7. Interior Enclosures: Provide temporary partitions as required to separate work areas from
Owner-occupied areas, to prevent penetration of dust and moisture into Owner-occupied areas,
and to prevent damage to existing materials and equipment.
8. Vehicular Access and Parking: Coordinate parking and haul routes with Owner.
9. Waste Removal: Provide waste removal facilities and services as required to maintain the site
in clean and orderly condition.
14-172-872-003-009
Summary Highlights of Scope of Work
Desired Outcome Understanding of Project scope.
Originated
Due
Resolved
Complete
Discussion Details
1. Demolition and replacement of exterior structural slab over basement area
2. Removal of abandoned fuel tank in basement area below structural tab
a. Remove and dispose tank, any contents and soil.
b. Remove and dispose masonry wall.
c. Remove and dispose concrete slab on-grade below tank
d. Remove and dispose 12" soil below removed slab on-grade.
e. Replace removed soil.
f. Replace slab on-grade.
Page 5 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
g. Provide and obtain all permits, reports, etc. as required.
h. Assume soils, slab on-grade, and masonry wall noted above to be removed is
contaminated and needs to be disposed of properly and legally.
3. Demolition and replacement of exterior site retaining wall.
4. Waterproofing of concrete walls.
5. Traffic coating for new structural slab over basement area.
6. Alternate Bid No. 1: Basement area below the slab will be filled in, foundations removed, water
proof door opening, in-filled and lab on grade installed for condusor.
No comments, all understand.
14-172-872-003-010
Summary Owner Comments
Desired Outcome Address any items not discussed.
Originated
Due
Resolved
Complete
Discussion Details
No Owner comments.
14-172-872-003-011
Summary Contractor Questions
Desired Outcome Address any items not discussed.
Originated
Due
Resolved
Complete
Discussion Details
Q1. Is testing for contaminants responsibility of Contractor?
A1. Bidding documents indicate who is responsible for testing.
Q2. Who is responsible for landscape restoration?
A2. Bidding documents indicate who is responsible for landscape restoration.
14-172-872-003-012
Summary Tour of Space
Desired
Outcome
Allow Contractors to view areas where work will be
performed.
Originated
Due
Resolved
Complete
Discussion Details
Tour of space was led by Jeff Bruns.
All information reported on this document is assumed to be accurate and correct. The
information on the document will remain on record unless changes are reported in writing
within seven (7) days of this report to the Kluber, Inc. office.
Page 6 of 7Meeting Minutes
8/26/2016https://secure.constructware.com/Common/View/Document_Display.asp?DocumentType=...
Supporting Documents
Document Type Document Open Description Date Size (KB)
Doc 14-172-872 Ph 1-00003 Sign in Sheets and cards 8/25/2016 606
Page 7 of 7Meeting Minutes