Loading...
2013 Water Main Tabulations_201303251003297110 238 south kenilworth avenue suite 100 oak park, illinois 60302 March 21, 2013 Mr. James Bosma, P.E. Village of Oak Brook 1200 Oak Brook Road Oak Brook, Illinois 60523 Re: 2013 Water Main Project Bid Proposals Evaluation Dear Mr. Bosma: Thomas Engineering Group, LLC (TEG) respectfully submits this letter to recommend a general contracting firm for performing contractual water main construction and restoration services for the 2013 Water Main Project. On Wednesday, March 20, 2013, the Village received and opened fourteen (14) bid proposals from interested firms. A Bid Tabulation worksheet (attached) was developed for evaluation of the lowest bidder based on the bid values submitted at the bid opening. Our evaluation of bids included consideration of the unit prices and past performance with other municipalities. Based on the attached tabulation, Suburban General Construction, Inc. (Suburban General) submitted the lowest overall cost proposal. Suburban General submitted a bid proposal value of $141,644.00, approximately twenty-nine (29) percent below the engineer’s total estimated cost, which was $199,155.50. The second lowest bid proposal, submitted by R.A. Mancini Contractors, was almost $8,000 higher than Suburban General’s bid proposal. Suburban General, located in LaGrange Park, IL, has performed work similar to the Village’s defined scope for other municipalities including the City of West Chicago. Thomas Engineering staff has not worked directly with Suburban General, but TEG called all references provided by Suburban General. All references reached by TEG indicated they had positive experiences with Suburban General. Based on this information, TEG believes that Suburban General performed work similar to the project’s scope and has the necessary equipment and qualified personnel to perform the required services. Suburban General is also registered by the Illinois Department of Transportation as a prequalified contractor able to perform earthwork, drainage, and concrete construction. This information can be found on IDOT’s website at: http://www.dot.state.il.us/const/subcontfirms.html Therefore, TEG hereby recommends you consider awarding the contract for the 2013 Water Main Project to the lowest responsible bidder, Suburban General Construction, Inc, for a contract amount not to exceed $141,644.00. If you have any questions or require additional information, please call me at (815) 531-7868 or by e-mail at nicko@thomas-engineering.com. Sincerely, thomas engineering group, llc Nicholas J. Orf, P.E., CFM, CPESC Attachments Page 1 of 5 PROJECT Village of Oak Brook - 2013 Water Main Project DATE:20-Mar-13 LOCATION 22nd Street (Hunter Drive)TIME:1:30PM SECTION: Prepared by:Glen Kirchen Note: 5% Bid Bonds included for all bids, errors shown in BOLD ITEM ESTIMATE ESTIMATE BID BID BID BID NO.UNIT COST TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL 1 PERIMETER EROSION BARRIER FOOT 755 $4.50 $3,397.50 $4.00 $3,020.00 $3.00 $2,265.00 2 INLET AND PIPE PROTECTION EACH 1 $200.00 $200.00 $250.00 $250.00 $150.00 $150.00 3 TOPSOIL FURNISH AND PLACE, 6"SQ YD 1237 $8.00 $9,896.00 $5.00 $6,185.00 $5.50 $6,803.50 4 SEEDING, CLASS 1A ACRE 0.3 $3,000.00 $900.00 $3,000.00 $900.00 $2,500.00 $750.00 5 EROSION CONTROL BLANKET SQ YD 1017 $2.00 $2,034.00 $2.00 $2,034.00 $3.00 $3,051.00 6 TURF REINFORCEMENT MAT SQ YD 220 $8.00 $1,760.00 $7.00 $1,540.00 $12.00 $2,640.00 7 PROTECTIVE COAT SQ YD 26 $5.00 $130.00 $2.00 $52.00 $3.00 $78.00 8 COMBINATION CURB AND GUTTER REMOVAL FOOT 52 $10.00 $520.00 $4.00 $208.00 $3.00 $156.00 9 SIDEWALK REMOVAL SQ FT 10 $15.00 $150.00 $1.00 $10.00 $1.00 $10.00 10 WATER VALVES 6"EACH 1 $2,500.00 $2,500.00 $3,000.00 $3,000.00 $2,700.00 $2,700.00 11 WATER VALVES 12"EACH 1 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $910.00 $910.00 12 FIRE HYDRANTS WITH AUXILIARY VALVE AND VALVE BOX EACH 1 $5,000.00 $5,000.00 $6,500.00 $6,500.00 $4,500.00 $4,500.00 13 VALVE VAULTS, TYPE A, 5'-DIAMETER, TYPE 1 FRAME, CLOSED LID EACH 2 $3,000.00 $6,000.00 $3,500.00 $7,000.00 $2,000.00 $4,000.00 14 VALVE VAULTS TO BE RECONSTRUCTED EACH 1 $2,000.00 $2,000.00 $700.00 $700.00 $200.00 $200.00 15 FILLING VALVE VAULTS EACH 1 $400.00 $400.00 $100.00 $100.00 $200.00 $200.00 16 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 (VARIABLE W FOOT 25 $40.00 $1,000.00 $40.00 $1,000.00 $36.00 $900.00 17 COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.12 FOOT 27 $25.00 $675.00 $40.00 $1,080.00 $36.00 $972.00 18 SHORT TERM PAVEMENT MARKING, 4"FOOT 100 $10.00 $1,000.00 $10.00 $1,000.00 $5.00 $500.00 19 PVC C-900 WATER MAIN, 12"FOOT 759 $70.00 $53,130.00 $60.00 $45,540.00 $51.00 $38,709.00 20 PVC C-900 WATER MAIN, 6"FOOT 14 $55.00 $770.00 $58.00 $812.00 $60.00 $840.00 21 EXTERNAL JOINT RESTRAINT FOR PVC C-900 WATER MAIN EACH 12 $400.00 $4,800.00 $250.00 $3,000.00 $210.00 $2,520.00 22 PRESSURE TESTING AND CHLORINATION OF WATER MAIN L SUM 1 $5,000.00 $5,000.00 $2,500.00 $2,500.00 $2,000.00 $2,000.00 23 NON-PRESSURE WATER MAIN CONNECTION "A"L SUM 1 $10,000.00 $10,000.00 $3,500.00 $3,500.00 $5,100.00 $5,100.00 24 NON-PRESSURE WATER MAIN CONNECTION "B"L SUM 1 $10,000.00 $10,000.00 $3,500.00 $3,500.00 $6,400.00 $6,400.00 25 WATER SERVICE CONNECTION, 6"L SUM 1 $5,000.00 $5,000.00 $3,500.00 $3,500.00 $2,500.00 $2,500.00 26 TRACER WIRE IN CONDUIT FOOT 759 $5.00 $3,795.00 $2.00 $1,518.00 $2.00 $1,518.00 27 TRACER WIRE ACCESS BOX EACH 3 $500.00 $1,500.00 $150.00 $450.00 $260.00 $780.00 28 STREET SWEEPING HOUR 20 $150.00 $3,000.00 $70.00 $1,400.00 $135.00 $2,700.00 29 WATER VALVE BOXES TO BE ABANDONED EACH 3 $100.00 $300.00 $100.00 $300.00 $150.00 $450.00 30 CLEANING PAVED DITCH FOOT 525 $6.00 $3,150.00 $7.00 $3,675.00 $5.00 $2,625.00 31 TRENCH BACKFILL, SPECIAL CU YD 630 $33.00 $20,790.00 $10.00 $6,300.00 $47.00 $29,610.00 32 EXPLORATION TRENCH, SPECIAL FOOT 40 $32.00 $1,280.00 $10.00 $400.00 $39.00 $1,560.00 33 PORTLAND CEMENT CONCRETE SIDEWALK, 5 INCH, SPECIAL SQ FT 100 $20.00 $2,000.00 $7.00 $700.00 $10.00 $1,000.00 34 BITUMINOUS BIKE PATH, 4"SQ FT 539 $8.00 $4,312.00 $6.00 $3,234.00 $6.00 $3,234.00 35 PAVEMENT REMOVAL (SPECIAL)SQ YD 349 $15.00 $5,235.00 $5.00 $1,745.00 $8.00 $2,792.00 36 ABANDON EXISTING WATER MAIN, FILL WITH CLSM FOOT 746 $10.00 $7,460.00 $10.00 $7,460.00 $6.50 $4,849.00 37 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 $5,000.00 $5,000.00 $3,000.00 $3,000.00 $2,500.00 $2,500.00 38 AGGREGATE SUBGRADE, 12"SQ YD 15 $30.00 $450.00 $35.00 $525.00 $10.00 $150.00 39 CONSTRUCTION LAYOUT L SUM 1 $1,500.00 $1,500.00 $2,400.00 $2,400.00 $1,000.00 $1,000.00 40 DUST CONTROL WATERING UNIT 20 $60.00 $1,200.00 $25.00 $500.00 $50.00 $1,000.00 41 SEDIMENT CONTROL, SILT FENCE FOOT 679 $4.00 $2,716.00 $4.00 $2,716.00 $3.00 $2,037.00 42 TEMPORARY PAVEMENT SQ YD 163 $35.00 $5,705.00 $30.00 $4,890.00 $18.00 $2,934.00 TOTAL $199,155.50 As Corrected $141,644.00 As Corrected $149,593.50 As Read $141,644.00 As Read $149,593.50 DESCRIPTION UNIT QUANTITY ENGINEER'S COST ESTIMATE SUBURBAN GENERAL R.A. MANCINI CONSTRUCTION,INC 1019 E. 31ST ST. LAGRANGE PK, IL 60526 708-354-0544 CONTRACTORS 2530 RTE. 176, SUITE 7 815-788-0400 PRAIRIE GROVE, IL 60012 Page 2 of 5 PROJECT Village of Oak Brook - 2013 Water Main Project DATE:20-Mar-13 LOCATION 22nd Street (Hunter Drive)TIME:1:30PM SECTION: Prepared by:Glen Kirchen Note: 5% Bid Bonds included for all bids, errors shown in BOLD ITEM NO. 1 PERIMETER EROSION BARRIER FOOT 755 2 INLET AND PIPE PROTECTION EACH 1 3 TOPSOIL FURNISH AND PLACE, 6"SQ YD 1237 4 SEEDING, CLASS 1A ACRE 0.3 5 EROSION CONTROL BLANKET SQ YD 1017 6 TURF REINFORCEMENT MAT SQ YD 220 7 PROTECTIVE COAT SQ YD 26 8 COMBINATION CURB AND GUTTER REMOVAL FOOT 52 9 SIDEWALK REMOVAL SQ FT 10 10 WATER VALVES 6"EACH 1 11 WATER VALVES 12"EACH 1 12 FIRE HYDRANTS WITH AUXILIARY VALVE AND VALVE BOX EACH 1 13 VALVE VAULTS, TYPE A, 5'-DIAMETER, TYPE 1 FRAME, CLOSED LID EACH 2 14 VALVE VAULTS TO BE RECONSTRUCTED EACH 1 15 FILLING VALVE VAULTS EACH 1 16 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 (VARIABLE W FOOT 25 17 COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.12 FOOT 27 18 SHORT TERM PAVEMENT MARKING, 4"FOOT 100 19 PVC C-900 WATER MAIN, 12"FOOT 759 20 PVC C-900 WATER MAIN, 6"FOOT 14 21 EXTERNAL JOINT RESTRAINT FOR PVC C-900 WATER MAIN EACH 12 22 PRESSURE TESTING AND CHLORINATION OF WATER MAIN L SUM 1 23 NON-PRESSURE WATER MAIN CONNECTION "A"L SUM 1 24 NON-PRESSURE WATER MAIN CONNECTION "B"L SUM 1 25 WATER SERVICE CONNECTION, 6"L SUM 1 26 TRACER WIRE IN CONDUIT FOOT 759 27 TRACER WIRE ACCESS BOX EACH 3 28 STREET SWEEPING HOUR 20 29 WATER VALVE BOXES TO BE ABANDONED EACH 3 30 CLEANING PAVED DITCH FOOT 525 31 TRENCH BACKFILL, SPECIAL CU YD 630 32 EXPLORATION TRENCH, SPECIAL FOOT 40 33 PORTLAND CEMENT CONCRETE SIDEWALK, 5 INCH, SPECIAL SQ FT 100 34 BITUMINOUS BIKE PATH, 4"SQ FT 539 35 PAVEMENT REMOVAL (SPECIAL)SQ YD 349 36 ABANDON EXISTING WATER MAIN, FILL WITH CLSM FOOT 746 37 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 38 AGGREGATE SUBGRADE, 12"SQ YD 15 39 CONSTRUCTION LAYOUT L SUM 1 40 DUST CONTROL WATERING UNIT 20 41 SEDIMENT CONTROL, SILT FENCE FOOT 679 42 TEMPORARY PAVEMENT SQ YD 163 DESCRIPTION UNIT QUANTITY BID BID BID BID BID BID UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL $2.00 $1,510.00 $10.00 $7,550.00 $2.00 $1,510.00 $160.00 $160.00 $125.00 $125.00 $200.00 $200.00 $4.00 $4,948.00 $5.00 $6,185.00 $5.00 $6,185.00 $1,600.00 $480.00 $3,000.00 $900.00 $300.00 $90.00 $2.00 $2,034.00 $2.00 $2,034.00 $3.00 $3,051.00 $6.00 $1,320.00 $5.50 $1,210.00 $5.00 $1,100.00 $10.00 $260.00 $5.00 $130.00 $3.00 $78.00 $24.00 $1,248.00 $7.00 $364.00 $3.00 $156.00 $2.00 $20.00 $2.00 $20.00 $10.00 $100.00 $900.00 $900.00 $1,000.00 $1,000.00 $1,400.00 $1,400.00 $2,750.00 $2,750.00 $2,000.00 $2,000.00 $2,500.00 $2,500.00 $6,650.00 $6,650.00 $4,000.00 $4,000.00 $3,900.00 $3,900.00 $2,020.00 $4,040.00 $1,500.00 $3,000.00 $1,600.00 $3,200.00 $1,200.00 $1,200.00 $500.00 $500.00 $1,200.00 $1,200.00 $300.00 $300.00 $200.00 $200.00 $200.00 $200.00 $35.00 $875.00 $40.00 $1,000.00 $28.00 $700.00 $30.00 $810.00 $40.00 $1,080.00 $26.00 $702.00 $6.00 $600.00 $1.20 $120.00 $20.00 $2,000.00 $68.00 $51,612.00 $64.00 $48,576.00 $64.00 $48,576.00 $50.00 $700.00 $80.00 $1,120.00 $50.00 $700.00 $140.00 $1,680.00 $250.00 $3,000.00 $150.00 $1,800.00 $1,600.00 $1,600.00 $1,500.00 $1,500.00 $1,000.00 $1,000.00 $4,600.00 $4,600.00 $2,500.00 $2,500.00 $3,000.00 $3,000.00 $4,000.00 $4,000.00 $3,500.00 $3,500.00 $4,000.00 $4,000.00 $4,600.00 $4,600.00 $2,500.00 $2,500.00 $2,500.00 $2,500.00 $2.50 $1,897.50 $2.00 $1,518.00 $6.00 $4,554.00 $100.00 $300.00 $125.00 $375.00 $300.00 $900.00 $110.00 $2,200.00 $105.00 $2,100.00 $95.00 $1,900.00 $200.00 $600.00 $200.00 $600.00 $50.00 $150.00 $18.00 $9,450.00 $7.00 $3,675.00 $5.00 $2,625.00 $12.00 $7,560.00 $30.00 $18,900.00 $42.00 $26,460.00 $30.00 $1,200.00 $10.00 $400.00 $15.00 $600.00 $6.00 $600.00 $8.00 $800.00 $5.50 $550.00 $5.00 $2,695.00 $4.00 $2,156.00 $32.00 $17,248.00 $10.00 $3,490.00 $8.00 $2,792.00 $5.00 $1,745.00 $10.00 $7,460.00 $6.00 $4,476.00 $9.00 $6,714.00 $6,000.00 $6,000.00 $30,000.00 $30,000.00 $4,500.00 $4,500.00 $15.00 $225.00 $30.00 $450.00 $14.00 $210.00 $1,400.00 $1,400.00 $500.00 $500.00 $1,500.00 $1,500.00 $100.00 $2,000.00 $10.00 $200.00 $25.00 $500.00 $2.00 $1,358.00 $0.10 $67.90 $2.00 $1,358.00 $38.00 $6,194.00 $15.00 $2,445.00 $12.00 $1,956.00 As Corrected $153,526.50 As Corrected $165,568.90 As Corrected $163,318.00 Difference $7,474.50 As Read $153,526.50 As Read $158,094.40 As Read $163,318.00 VIAN J. CONGDON CONSTRUCTION, INC. 1041 MARTHA ELK GROVE VILLAGE, IL 60007 847-364-5369 SEWER SERVICE INC. 170-A ALEXANDRA WAY CAROL STREAM, IL 60188 630-510-2434 PATNICK CONSTRUCTION 431 PODLIN DR FRANKLIN PARK, IL 60131 847-910-5400 Page 3 of 5 PROJECT Village of Oak Brook - 2013 Water Main Project DATE:20-Mar-13 LOCATION 22nd Street (Hunter Drive)TIME:1:30PM SECTION: Prepared by:Glen Kirchen Note: 5% Bid Bonds included for all bids, errors shown in BOLD ITEM NO. 1 PERIMETER EROSION BARRIER FOOT 755 2 INLET AND PIPE PROTECTION EACH 1 3 TOPSOIL FURNISH AND PLACE, 6"SQ YD 1237 4 SEEDING, CLASS 1A ACRE 0.3 5 EROSION CONTROL BLANKET SQ YD 1017 6 TURF REINFORCEMENT MAT SQ YD 220 7 PROTECTIVE COAT SQ YD 26 8 COMBINATION CURB AND GUTTER REMOVAL FOOT 52 9 SIDEWALK REMOVAL SQ FT 10 10 WATER VALVES 6"EACH 1 11 WATER VALVES 12"EACH 1 12 FIRE HYDRANTS WITH AUXILIARY VALVE AND VALVE BOX EACH 1 13 VALVE VAULTS, TYPE A, 5'-DIAMETER, TYPE 1 FRAME, CLOSED LID EACH 2 14 VALVE VAULTS TO BE RECONSTRUCTED EACH 1 15 FILLING VALVE VAULTS EACH 1 16 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 (VARIABLE W FOOT 25 17 COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.12 FOOT 27 18 SHORT TERM PAVEMENT MARKING, 4"FOOT 100 19 PVC C-900 WATER MAIN, 12"FOOT 759 20 PVC C-900 WATER MAIN, 6"FOOT 14 21 EXTERNAL JOINT RESTRAINT FOR PVC C-900 WATER MAIN EACH 12 22 PRESSURE TESTING AND CHLORINATION OF WATER MAIN L SUM 1 23 NON-PRESSURE WATER MAIN CONNECTION "A"L SUM 1 24 NON-PRESSURE WATER MAIN CONNECTION "B"L SUM 1 25 WATER SERVICE CONNECTION, 6"L SUM 1 26 TRACER WIRE IN CONDUIT FOOT 759 27 TRACER WIRE ACCESS BOX EACH 3 28 STREET SWEEPING HOUR 20 29 WATER VALVE BOXES TO BE ABANDONED EACH 3 30 CLEANING PAVED DITCH FOOT 525 31 TRENCH BACKFILL, SPECIAL CU YD 630 32 EXPLORATION TRENCH, SPECIAL FOOT 40 33 PORTLAND CEMENT CONCRETE SIDEWALK, 5 INCH, SPECIAL SQ FT 100 34 BITUMINOUS BIKE PATH, 4"SQ FT 539 35 PAVEMENT REMOVAL (SPECIAL)SQ YD 349 36 ABANDON EXISTING WATER MAIN, FILL WITH CLSM FOOT 746 37 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 38 AGGREGATE SUBGRADE, 12"SQ YD 15 39 CONSTRUCTION LAYOUT L SUM 1 40 DUST CONTROL WATERING UNIT 20 41 SEDIMENT CONTROL, SILT FENCE FOOT 679 42 TEMPORARY PAVEMENT SQ YD 163 DESCRIPTION UNIT QUANTITY BID BID BID BID BID BID UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL $3.30 $2,491.50 $3.00 $2,265.00 $4.50 $3,397.50 $200.00 $200.00 $150.00 $150.00 $250.00 $250.00 $4.40 $5,442.80 $5.00 $6,185.00 $5.50 $6,803.50 $2,640.00 $792.00 $10,000.00 $3,000.00 $5,000.00 $1,500.00 $3.30 $3,356.10 $4.00 $4,068.00 $2.00 $2,034.00 $19.80 $4,356.00 $10.00 $2,200.00 $7.00 $1,540.00 $2.10 $54.60 $2.00 $52.00 $3.00 $78.00 $4.00 $208.00 $10.00 $520.00 $6.00 $312.00 $5.00 $50.00 $10.00 $100.00 $3.00 $30.00 $900.00 $900.00 $1,500.00 $1,500.00 $1,200.00 $1,200.00 $2,350.00 $2,350.00 $2,800.00 $2,800.00 $2,700.00 $2,700.00 $3,800.00 $3,800.00 $3,800.00 $3,800.00 $5,000.00 $5,000.00 $2,000.00 $4,000.00 $1,750.00 $3,500.00 $2,457.00 $4,914.00 $1,200.00 $1,200.00 $1,000.00 $1,000.00 $500.00 $500.00 $100.00 $100.00 $200.00 $200.00 $850.00 $850.00 $35.00 $875.00 $40.00 $1,000.00 $35.00 $875.00 $35.00 $945.00 $35.00 $945.00 $35.00 $945.00 $1.50 $150.00 $3.00 $300.00 $2.00 $200.00 $52.25 $39,657.75 $47.00 $35,673.00 $67.00 $50,853.00 $60.00 $840.00 $45.00 $630.00 $45.00 $630.00 $180.00 $2,160.00 $350.00 $4,200.00 $300.00 $3,600.00 $1,200.00 $1,200.00 $1,500.00 $1,500.00 $1,400.00 $1,400.00 $4,200.00 $4,200.00 $13,000.00 $13,000.00 $5,143.00 $5,143.00 $4,200.00 $4,200.00 $12,500.00 $12,500.00 $10,430.00 $10,430.00 $1,800.00 $1,800.00 $3,000.00 $3,000.00 $4,474.00 $4,474.00 $4.00 $3,036.00 $2.00 $1,518.00 $5.85 $4,440.15 $80.00 $240.00 $100.00 $300.00 $100.00 $300.00 $225.00 $4,500.00 $30.00 $600.00 $90.00 $1,800.00 $100.00 $300.00 $100.00 $300.00 $75.00 $225.00 $20.00 $10,500.00 $3.00 $1,575.00 $7.00 $3,675.00 $35.00 $22,050.00 $35.00 $22,050.00 $27.00 $17,010.00 $30.00 $1,200.00 $25.00 $1,000.00 $20.00 $800.00 $8.80 $880.00 $10.00 $1,000.00 $11.00 $1,100.00 $8.00 $4,312.00 $5.00 $2,695.00 $4.40 $2,371.60 $20.00 $6,980.00 $6.00 $2,094.00 $15.00 $5,235.00 $15.00 $11,190.00 $5.00 $3,730.00 $17.00 $12,682.00 $3,600.00 $3,600.00 $19,000.00 $19,000.00 $5,100.00 $5,100.00 $50.00 $750.00 $20.00 $300.00 $35.00 $525.00 $1,600.00 $1,600.00 $5,000.00 $5,000.00 $2,800.00 $2,800.00 $100.00 $2,000.00 $10.00 $200.00 $100.00 $2,000.00 $3.50 $2,376.50 $3.00 $2,037.00 $4.50 $3,055.50 $30.00 $4,890.00 $12.00 $1,956.00 $17.00 $2,771.00 As Corrected $165,733.25 As Corrected $169,443.00 As Corrected $175,549.25 As Read $165,733.25 As Read $169,443.00 As Read $175,549.25 CHICAGO, IL 60630 773-736-0607 CITY CONSTRUCTION CO UNIQUE PLUMBING COM. 9408 W. 47TH ST. BROOKFIELD, IL 708-485-8860 DIMEO BROTHERS 720 RICHARD LANE ELK GROVE VILLAGE 847-640-2240 4403 W. LAWRENCE AVE SUITE 205 Page 4 of 5 PROJECT Village of Oak Brook - 2013 Water Main Project DATE:20-Mar-13 LOCATION 22nd Street (Hunter Drive)TIME:1:30PM SECTION: Prepared by:Glen Kirchen Note: 5% Bid Bonds included for all bids, errors shown in BOLD ITEM NO. 1 PERIMETER EROSION BARRIER FOOT 755 2 INLET AND PIPE PROTECTION EACH 1 3 TOPSOIL FURNISH AND PLACE, 6"SQ YD 1237 4 SEEDING, CLASS 1A ACRE 0.3 5 EROSION CONTROL BLANKET SQ YD 1017 6 TURF REINFORCEMENT MAT SQ YD 220 7 PROTECTIVE COAT SQ YD 26 8 COMBINATION CURB AND GUTTER REMOVAL FOOT 52 9 SIDEWALK REMOVAL SQ FT 10 10 WATER VALVES 6"EACH 1 11 WATER VALVES 12"EACH 1 12 FIRE HYDRANTS WITH AUXILIARY VALVE AND VALVE BOX EACH 1 13 VALVE VAULTS, TYPE A, 5'-DIAMETER, TYPE 1 FRAME, CLOSED LID EACH 2 14 VALVE VAULTS TO BE RECONSTRUCTED EACH 1 15 FILLING VALVE VAULTS EACH 1 16 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 (VARIABLE W FOOT 25 17 COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.12 FOOT 27 18 SHORT TERM PAVEMENT MARKING, 4"FOOT 100 19 PVC C-900 WATER MAIN, 12"FOOT 759 20 PVC C-900 WATER MAIN, 6"FOOT 14 21 EXTERNAL JOINT RESTRAINT FOR PVC C-900 WATER MAIN EACH 12 22 PRESSURE TESTING AND CHLORINATION OF WATER MAIN L SUM 1 23 NON-PRESSURE WATER MAIN CONNECTION "A"L SUM 1 24 NON-PRESSURE WATER MAIN CONNECTION "B"L SUM 1 25 WATER SERVICE CONNECTION, 6"L SUM 1 26 TRACER WIRE IN CONDUIT FOOT 759 27 TRACER WIRE ACCESS BOX EACH 3 28 STREET SWEEPING HOUR 20 29 WATER VALVE BOXES TO BE ABANDONED EACH 3 30 CLEANING PAVED DITCH FOOT 525 31 TRENCH BACKFILL, SPECIAL CU YD 630 32 EXPLORATION TRENCH, SPECIAL FOOT 40 33 PORTLAND CEMENT CONCRETE SIDEWALK, 5 INCH, SPECIAL SQ FT 100 34 BITUMINOUS BIKE PATH, 4"SQ FT 539 35 PAVEMENT REMOVAL (SPECIAL)SQ YD 349 36 ABANDON EXISTING WATER MAIN, FILL WITH CLSM FOOT 746 37 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 38 AGGREGATE SUBGRADE, 12"SQ YD 15 39 CONSTRUCTION LAYOUT L SUM 1 40 DUST CONTROL WATERING UNIT 20 41 SEDIMENT CONTROL, SILT FENCE FOOT 679 42 TEMPORARY PAVEMENT SQ YD 163 DESCRIPTION UNIT QUANTITY BID BID BID BID BID BID UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL $3.50 $2,642.50 $2.55 $1,925.25 $4.00 $3,020.00 $250.00 $250.00 $44.80 $44.80 $2,000.00 $2,000.00 $6.00 $7,422.00 $5.65 $6,989.05 $7.00 $8,659.00 $20,000.00 $6,000.00 $7,339.00 $2,201.70 $5,000.00 $1,500.00 $4.00 $4,068.00 $2.80 $2,847.60 $4.00 $4,068.00 $10.00 $2,200.00 $56.00 $12,320.00 $6.00 $1,320.00 $7.00 $182.00 $5.50 $143.00 $3.00 $78.00 $12.00 $624.00 $5.50 $286.00 $11.00 $572.00 $10.00 $100.00 $5.50 $55.00 $5.00 $50.00 $1,300.00 $1,300.00 $1,440.00 $1,440.00 $1,230.00 $1,230.00 $3,000.00 $3,000.00 $3,135.00 $3,135.00 $3,150.00 $3,150.00 $4,500.00 $4,500.00 $4,857.00 $4,857.00 $5,200.00 $5,200.00 $2,800.00 $5,600.00 $1,841.50 $3,683.00 $2,750.00 $5,500.00 $500.00 $500.00 $785.50 $785.50 $1,300.00 $1,300.00 $400.00 $400.00 $744.00 $744.00 $715.00 $715.00 $75.00 $1,875.00 $57.80 $1,445.00 $40.00 $1,000.00 $50.00 $1,350.00 $57.80 $1,560.60 $38.00 $1,026.00 $7.00 $700.00 $4.30 $430.00 $2.00 $200.00 $78.00 $59,202.00 $113.80 $86,374.20 $86.00 $65,274.00 $30.00 $420.00 $110.10 $1,541.40 $68.00 $952.00 $300.00 $3,600.00 $215.00 $2,580.00 $315.00 $3,780.00 $1,500.00 $1,500.00 $2,690.00 $2,690.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $3,557.00 $3,557.00 $6,500.00 $6,500.00 $6,000.00 $6,000.00 $3,685.80 $3,685.80 $6,000.00 $6,000.00 $4,500.00 $4,500.00 $3,557.00 $3,557.00 $5,100.00 $5,100.00 $1.00 $759.00 $3.70 $2,808.30 $2.00 $1,518.00 $100.00 $300.00 $167.90 $503.70 $140.00 $420.00 $120.00 $2,400.00 $144.10 $2,882.00 $110.00 $2,200.00 $500.00 $1,500.00 $163.10 $489.30 $100.00 $300.00 $10.00 $5,250.00 $25.80 $13,545.00 $11.00 $5,775.00 $43.00 $27,090.00 $1.10 $693.00 $34.00 $21,420.00 $25.00 $1,000.00 $31.90 $1,276.00 $100.00 $4,000.00 $7.00 $700.00 $10.75 $1,075.00 $10.00 $1,000.00 $5.00 $2,695.00 $4.15 $2,236.85 $10.00 $5,390.00 $2.50 $872.50 $16.50 $5,758.50 $12.00 $4,188.00 $10.00 $7,460.00 $10.75 $8,019.50 $20.00 $14,920.00 $8,000.00 $8,000.00 $1,523.95 $1,523.95 $11,000.00 $11,000.00 $25.00 $375.00 $27.50 $412.50 $33.00 $495.00 $1,500.00 $1,500.00 $2,455.25 $2,455.25 $4,000.00 $4,000.00 $40.00 $800.00 $1.10 $22.00 $150.00 $3,000.00 $3.50 $2,376.50 $2.55 $1,731.45 $4.00 $2,716.00 $45.00 $7,335.00 $16.50 $2,689.50 $20.00 $3,260.00 As Corrected $193,348.50 As Corrected $196,999.70 As Corrected $218,796.00 As Read $193,348.50 As Read $197,000.00 As Read $218,800.00 PALOS PARK, IL 60464 708-774-4995 CONSTRUCTION CORP. 27W364 NORTH AVENUE RICCIO CONSTRUCTION CORP. P.O. BOX 672 CONLEY EXCAVATING 1555 GRAMERCY PL MORRIS, IL 60450 TRINE WEST CHICAGO, IL 60185 Page 5 of 5 PROJECT Village of Oak Brook - 2013 Water Main Project DATE:20-Mar-13 LOCATION 22nd Street (Hunter Drive)TIME:1:30PM SECTION: Prepared by:Glen Kirchen Note: 5% Bid Bonds included for all bids, errors shown in BOLD ITEM NO. 1 PERIMETER EROSION BARRIER FOOT 755 2 INLET AND PIPE PROTECTION EACH 1 3 TOPSOIL FURNISH AND PLACE, 6"SQ YD 1237 4 SEEDING, CLASS 1A ACRE 0.3 5 EROSION CONTROL BLANKET SQ YD 1017 6 TURF REINFORCEMENT MAT SQ YD 220 7 PROTECTIVE COAT SQ YD 26 8 COMBINATION CURB AND GUTTER REMOVAL FOOT 52 9 SIDEWALK REMOVAL SQ FT 10 10 WATER VALVES 6"EACH 1 11 WATER VALVES 12"EACH 1 12 FIRE HYDRANTS WITH AUXILIARY VALVE AND VALVE BOX EACH 1 13 VALVE VAULTS, TYPE A, 5'-DIAMETER, TYPE 1 FRAME, CLOSED LID EACH 2 14 VALVE VAULTS TO BE RECONSTRUCTED EACH 1 15 FILLING VALVE VAULTS EACH 1 16 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.24 (VARIABLE W FOOT 25 17 COMBINATION CONCRETE CURB AND GUTTER, TYPE M-6.12 FOOT 27 18 SHORT TERM PAVEMENT MARKING, 4"FOOT 100 19 PVC C-900 WATER MAIN, 12"FOOT 759 20 PVC C-900 WATER MAIN, 6"FOOT 14 21 EXTERNAL JOINT RESTRAINT FOR PVC C-900 WATER MAIN EACH 12 22 PRESSURE TESTING AND CHLORINATION OF WATER MAIN L SUM 1 23 NON-PRESSURE WATER MAIN CONNECTION "A"L SUM 1 24 NON-PRESSURE WATER MAIN CONNECTION "B"L SUM 1 25 WATER SERVICE CONNECTION, 6"L SUM 1 26 TRACER WIRE IN CONDUIT FOOT 759 27 TRACER WIRE ACCESS BOX EACH 3 28 STREET SWEEPING HOUR 20 29 WATER VALVE BOXES TO BE ABANDONED EACH 3 30 CLEANING PAVED DITCH FOOT 525 31 TRENCH BACKFILL, SPECIAL CU YD 630 32 EXPLORATION TRENCH, SPECIAL FOOT 40 33 PORTLAND CEMENT CONCRETE SIDEWALK, 5 INCH, SPECIAL SQ FT 100 34 BITUMINOUS BIKE PATH, 4"SQ FT 539 35 PAVEMENT REMOVAL (SPECIAL)SQ YD 349 36 ABANDON EXISTING WATER MAIN, FILL WITH CLSM FOOT 746 37 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 38 AGGREGATE SUBGRADE, 12"SQ YD 15 39 CONSTRUCTION LAYOUT L SUM 1 40 DUST CONTROL WATERING UNIT 20 41 SEDIMENT CONTROL, SILT FENCE FOOT 679 42 TEMPORARY PAVEMENT SQ YD 163 DESCRIPTION UNIT QUANTITY BID BID BID BID BID BID UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL $4.60 $3,473.00 $2.50 $1,887.50 $2.00 $1,510.00 $290.00 $290.00 $350.00 $350.00 $200.00 $200.00 $8.10 $10,019.70 $13.00 $16,081.00 $8.00 $9,896.00 $3,703.30 $1,110.99 $3,390.00 $1,017.00 $4,100.00 $1,230.00 $5.80 $5,898.60 $4.65 $4,729.05 $4.00 $4,068.00 $4.60 $1,012.00 $18.00 $3,960.00 $5.00 $1,100.00 $2.30 $59.80 $5.10 $132.60 $17.00 $442.00 $8.10 $421.20 $21.50 $1,118.00 $28.00 $1,456.00 $2.10 $21.00 $10.00 $100.00 $8.00 $80.00 $1,104.00 $1,104.00 $900.00 $900.00 $900.00 $900.00 $2,612.00 $2,612.00 $2,500.00 $2,500.00 $2,600.00 $2,600.00 $5,211.00 $5,211.00 $4,100.00 $4,100.00 $4,550.00 $4,550.00 $2,076.50 $4,153.00 $1,860.00 $3,720.00 $3,960.00 $7,920.00 $1,440.00 $1,440.00 $1,860.00 $1,860.00 $1,295.00 $1,295.00 $498.00 $498.00 $900.00 $900.00 $356.00 $356.00 $34.80 $870.00 $50.00 $1,250.00 $77.00 $1,925.00 $34.80 $939.60 $40.00 $1,080.00 $75.00 $2,025.00 $1.70 $170.00 $10.00 $1,000.00 $4.50 $450.00 $59.50 $45,160.50 $95.00 $72,105.00 $60.00 $45,540.00 $41.30 $578.20 $50.00 $700.00 $51.00 $714.00 $261.70 $3,140.40 $141.00 $1,692.00 $226.00 $2,712.00 $4,954.00 $4,954.00 $650.00 $650.00 $3,390.00 $3,390.00 $6,345.00 $6,345.00 $4,530.00 $4,530.00 $4,530.00 $4,530.00 $6,708.00 $6,708.00 $5,350.00 $5,350.00 $2,380.00 $2,380.00 $4,208.00 $4,208.00 $4,530.00 $4,530.00 $2,440.00 $2,440.00 $0.49 $371.91 $1.50 $1,138.50 $3.00 $2,277.00 $50.00 $150.00 $22.60 $67.80 $103.00 $309.00 $290.00 $5,800.00 $565.00 $11,300.00 $150.00 $3,000.00 $268.30 $804.90 $82.00 $246.00 $150.00 $450.00 $25.20 $13,230.00 $4.00 $2,100.00 $9.00 $4,725.00 $61.50 $38,745.00 $46.00 $28,980.00 $60.00 $37,800.00 $122.70 $4,908.00 $105.00 $4,200.00 $100.00 $4,000.00 $9.30 $930.00 $10.00 $1,000.00 $23.00 $2,300.00 $4.60 $2,479.40 $13.00 $7,007.00 $9.00 $4,851.00 $22.40 $7,817.60 $16.00 $5,584.00 $20.00 $6,980.00 $12.70 $9,474.20 $7.00 $5,222.00 $27.00 $20,142.00 $10,135.00 $10,135.00 $1,764.55 $1,764.55 $9,000.00 $9,000.00 $39.20 $588.00 $41.50 $622.50 $50.00 $750.00 $3,155.30 $3,155.30 $2,500.00 $2,500.00 $6,000.00 $6,000.00 $290.00 $5,800.00 $220.00 $4,400.00 $450.00 $9,000.00 $3.50 $2,376.50 $2.50 $1,697.50 $2.00 $1,358.00 $17.40 $2,836.20 $50.00 $8,150.00 $45.00 $7,335.00 As Corrected $220,000.00 As Corrected $222,222.00 As Corrected $223,986.00 As Read $220,000.00 As Read $222,222.00 As Read $223,986.00 ARCHON CONSTRUCTION INC. 563 SOUTH ROUTE 53 ADDISON, IL 60101 630-495-0015 X126 STIP BROS. EXCAVATING, INC. 19042 W. MANHATTAN RD ELWOOD, IL 60421 815-423-5877 PIRTANO CONSTRUCTION 1766 ARMITAGE CT ADDISON, IL 630-932-1810