Projects Update 7-14-23.docx
Project Updates for the Week of July 16, 2023
Updated July 14, 2023
Hydrant flushing has been paused as of July 14th and is tentatively
scheduled to kick off again during the month of September.
The condition of the York Road bridge deck over the I-88 / I-294 connector
ramp continues to be monitored and patched as needed. The Village is in
the process of coordinating the deck and superstructure replacement with
the Tollway.
The Village has been notified by the DuPage County Division of
Transportation that Midwest Road/Summit Ave, which are their
highways, are scheduled to be improved/resurfaced during the 2023
construction season. If you have questions, please contact DuPage
County at 630-407-6900 or email dot@dupageco.org.
Flagg Creek Water Reclamation District is in the process of installing a lift
station at Harger Road, east of Spring Road. For information, please
contact Flagg Creek at 630-323-3299.