Projects Update 11.5.23.docx Project Updates for the Week of November 5th, 2023 Updated November 3rd, 2023  The resurfacing project of Harger Road from Spring Road to the westbound I-88 entrance ramp is essentially complete with some minor landscape restoration remaining that may require intermittent lane closures during the day. For more information or answers to your questions, please feel free to call the Resident Engineer, Raz Calin, at 224- 240-2998 or the Project Manager, Orion Galey, at 847-833-0210. You may also contact Public Works at 630-368-5270.  The condition of the York Road bridge deck over the I-88 / I-294 connector ramp continues to be monitored and patched as needed. The Village continues to coordinate the deck and superstructure replacement with the Illinois Tollway Authority.  Flagg Creek Water Reclamation District is in the process of installing a lift station at Harger Road east of Spring Road. For more information, please contact Flagg Creek at 630-323-3299.